HVDC Haenam–Cheju

From Wikipedia, the free encyclopedia
Haenam–Cheju HVDC system
Location
CountryKorea
Coordinates34°22′03″N 126°35′34″E / 34.36750°N 126.59278°E / 34.36750; 126.59278 (Haenam Converter Station)
33°32′06″N 126°35′44″E / 33.53500°N 126.59556°E / 33.53500; 126.59556 (Jeju Converter Station)
FromHaenam
ToJeju Island
Ownership information
OwnerKorea Electric Power Corporation
Construction information
Manufacturer of substationsAlstom
Commissioned1996; 28 years ago (1996)
Technical information
TypeTransmission
Type of currentHVDC
Total length101 km (63 mi)
Power rating300 MW
DC voltage±180 kV
No. of poles2

The HVDC Haenam–Cheju is a 101 kilometer long HVDC submarine cable connection between the Korean Peninsula and the island of Jeju (spelled Cheju until 2000) in South Korea, which went into service in 1996. The connection is bipolar, consisting of two 180kV cables with a maximum transmission power of 300 megawatts.

The Haenam–Cheju HVDC system is owned and operated by Korea Electric Power Corporation (KEPCO).

The line runs from the Haenam converter station situated at 34°22′03″N 126°35′34″E / 34.36750°N 126.59278°E / 34.36750; 126.59278 (Haenam Converter Station) to Jeju converter station at 33°32′06″N 126°35′44″E / 33.53500°N 126.59556°E / 33.53500; 126.59556 (Jeju Converter Station) and has no overhead line sections. The first 5 kilometres on Korean Mainland are underground, the rest of the cable is laid partially buried in the sea. As the converter station on Jeju is close to the sea, all equipment (even the AC harmonic filters) is installed indoors in order to prevent corrosion and pollution-related flashovers from sea salt.[1]

The system is designed to take over the full power supply of Jeju and is therefore equipped with synchronous compensators delivering the required reactive power and commutation voltage when there is no generation unit at Jeju in operation.[2] These synchronous compensators can be started with gas turbines, which allows starting and subsequently running the HVDC transmission scheme when there is no generation available on the island.

The HVDC scheme includes several unusual design features arising from the design objective of using the HVDC link as the sole source of power to Jeju, in which mode it must define the frequency of the island system. For this reason the inverter on Jeju island must be able to control the received power rapidly without reliance on telecommunications to the mainland. As a result, the control characteristics are reversed from the conventional practice, the inverter (Jeju) station controlling current and the rectifier (Haenam) station controlling DC voltage. The thyristor valves are also designed to operate with a minimum power down to zero (compared with the usual minimum of 5-10%).

See also

[edit]

References